Project cargo and heavy lift

30-metre steel piles, Cilegon to Tanah Bumbu

Thirty-metre steel piles for a jetty construction project, delivered door to door from the factory in Cilegon to the project site in Tanah Bumbu, South Kalimantan, using boogie trailers and a 250-foot barge.

Crane lifting steel piles onto the barge at the loading port
Cargo
Steel piles
Origin
Cilegon, Banten
Destination
Tanah Bumbu, South Kalimantan
Transport mode
Multimodal: road + barge
Documented
March 2024
Operation data

Key figures

Length
30 metres
Diameter
1,200 mm
Road fleet
Boogie trailers
Barge
250 feet
Loading crane
80-ton capacity
Sailing time
±12 days
Service scope
Dari pintu ke pintu, sampai di lokasi proyek

Stage by stage

37 photos from the operation. Select a photo to view it full size.

  1. 01

    Loading at the Cilegon factory

    The piles were lifted by crane onto boogie trailers at the factory, then hauled to the nearest port.

    Steel piles loaded onto boogie trailers by crane at the Cilegon factory (1/10)Steel piles loaded onto boogie trailers by crane at the Cilegon factory (2/10)Steel piles loaded onto boogie trailers by crane at the Cilegon factory (3/10)Steel piles loaded onto boogie trailers by crane at the Cilegon factory (4/10)Steel piles loaded onto boogie trailers by crane at the Cilegon factory (5/10)Steel piles loaded onto boogie trailers by crane at the Cilegon factory (6/10)Steel piles loaded onto boogie trailers by crane at the Cilegon factory (7/10)Steel piles loaded onto boogie trailers by crane at the Cilegon factory (8/10)Steel piles loaded onto boogie trailers by crane at the Cilegon factory (9/10)Steel piles loaded onto boogie trailers by crane at the Cilegon factory (10/10)

    Original post on Instagram

  2. 02

    Unloading at the port yard

    At the port the piles were unloaded into a temporary stacking yard while the 250-foot barge was brought alongside.

    Steel piles unloaded and stacked at the port yard (1/10)Steel piles unloaded and stacked at the port yard (2/10)Steel piles unloaded and stacked at the port yard (3/10)Steel piles unloaded and stacked at the port yard (4/10)Steel piles unloaded and stacked at the port yard (5/10)Steel piles unloaded and stacked at the port yard (6/10)Steel piles unloaded and stacked at the port yard (7/10)Steel piles unloaded and stacked at the port yard (8/10)Steel piles unloaded and stacked at the port yard (9/10)Steel piles unloaded and stacked at the port yard (10/10)

    Original post on Instagram

  3. 03

    Loading onto the barge

    The piles were loaded onto the barge with an 80-ton crane so the lift could reach the far side of the deck. Once the loading port's safety requirements were met, the vessel received its sailing clearance for Tanah Bumbu.

    Crane lifting steel piles onto the barge at the loading port (1/9)Crane lifting steel piles onto the barge at the loading port (2/9)Crane lifting steel piles onto the barge at the loading port (3/9)Crane lifting steel piles onto the barge at the loading port (4/9)Crane lifting steel piles onto the barge at the loading port (5/9)Crane lifting steel piles onto the barge at the loading port (6/9)Crane lifting steel piles onto the barge at the loading port (7/9)Crane lifting steel piles onto the barge at the loading port (8/9)Crane lifting steel piles onto the barge at the loading port (9/9)

    Original post on Instagram

  4. 04

    Material on site

    After roughly 12 days at sea the barge berthed at the project's private jetty. The piles were discharged and moved to the owner's stock yard, about 1 km from the berth.

    Steel piles discharged from the barge at the Tanah Bumbu jetty project site (1/8)Steel piles discharged from the barge at the Tanah Bumbu jetty project site (2/8)Steel piles discharged from the barge at the Tanah Bumbu jetty project site (3/8)Steel piles discharged from the barge at the Tanah Bumbu jetty project site (4/8)Steel piles discharged from the barge at the Tanah Bumbu jetty project site (5/8)Steel piles discharged from the barge at the Tanah Bumbu jetty project site (6/8)Steel piles discharged from the barge at the Tanah Bumbu jetty project site (7/8)Steel piles discharged from the barge at the Tanah Bumbu jetty project site (8/8)

    Original post on Instagram

Related service

Project Cargo & Heavy Lift

End-to-end management for heavy equipment, industrial machinery, steel piles, and project structures. Road transport, barges, and crane lifts coordinated under single oversight to site.

View service

Discuss a similar project

Send the cargo dimensions, weight, route, required date, and site conditions for an initial assessment.

Request a Project Quote